Detailed Engineering Design Services for EPCIC of PM309 Gas Ledang Segment 2 Development Project
Client

Contractor

Duration
June 2020
-
October 2021
PM 309 Ledang gas facilities is located offshore Terengganu. The Ledang Phase 2 development installed new facilities that includes :
-
1 x subsea tree and wellhead
-
1 x 2.3km Flowline and umbilical from Ledang to LDP-A
-
Host Tie-In and Modification at LDP-A.
The detailed engineering scope includes:
-
Subsea Christmas Tree, Wellhead, flow base and tooling
-
All subsea tree and tubing hanger tooling, IWOCS (including hydraulic fluids and other consumables) and ROV/Diver tooling for subsea tree installation
-
Procedures for simultaneous operations (SIMOP) activities