top of page
Front End Engineering Design Services for Sarawak Model Project (for more than 20 Platforms for Oil and Gas Services)
Client

Duration
June 2024
-
Ongoing
Cengkih field is located in part of SK-320 Block PSC located in the Central Luconia province 250 km offshore Sarawak. Pegaga which is the central hub of the block and began production in 2022. Other fields Sintok, Sireh and M5 are being developed and are envisioned to tie back to Pegaga.
DAR was awarded the project for Cengkih concept select and Pegaga satellites feasibility study, to determine the followings:
-
Evaluate development options and rank against key value drivers
-
Select one development concept for Cengkih that is robust and meet the project objectives.
-
Prepare Scope of Work and ITB package for the next phase of engineering study (“FEED”) and MR4 preparatory work.
Technology & Innovation: Key Highlights Projects
bottom of page